Field engineer for the Castoro II DLB means multi-purpose fleet of Saipem, platform installation and spool:
- LTA PROJECT - SPOOL INSTALLATION
The project includes the installation of a production spool and a tie-in spool.
The following activities were performed and supervised during the installation phase:
- Preparation to install the spool
- Calculation the length of the spool
- Spool prefabrication on board
- Installation and connection of the spool between the existing line and the riser by divers
CLIENT: SAUDI ARAMCO
- LTA PROJECT - INSTALLATION OF PLATFORM ZULF 480-489
The project includes the installation of a drilling platform on an existing jacket. The following activities were monitored and supervised during installation on board:
- Preparation activities for the installation of the platform, e.g. removal of the parts on the jacket for the installation of the platform
- Supervise installation tasks as lifting, positioning and welding of the legs of the platform with the jacket
- Completion works on the jacket, e.g. removal of the pad-eye for the platform lifting, installation of stairs leading to the platform, welding of plates and beams to connect the platform with the existing drill deck.
CLIENT: SAUDI ARAMCO
- LTA PROJECT - INSTALLATION OF PLATFORM ZULF 490-499
The project includes the installation of a drilling platform on an existing jacket. The following activities were monitored and supervised during installation on board:
- Preparation activities for the installation of the platform, e.g. removal of the parts on the jacket for the installation of the platform
- Supervise installation tasks as lifting, positioning and welding of the legs of the platform with the jacket
- Completion works on the jacket, e.g. removal of the pad-eye for the platform lifting, installation of stairs leading to the platform, welding of plates and beams to connect the platform with the existing drill deck.
CLIENT: SAUDI ARAMCO
- LTA PROJECT - INSTALLING THE JACKET MRJN 420 \ 429
The project includes the installation of a jacket with 4 legs and 3 bays in Marjan field of Persian Gulf. The following activities were performed and supervised during the installation:
- Preparation activities for jacket installation and survey of the installation area
- Lifting, upending and positioning of the platform at the final position
- Jecket levelling
- Foundation piles installation: positioning, stabbing, hammering, add-on stabbing, welding and hammering until the target box. Installation of the piles according to the sequence
- Cutting portion of the piles for installation of transition pieces
- Installation of conductors piles according to the procedure
- Installing TDD, boatlanding and transition piece
- Completion work with installation of walkways, stairs, gratings, handrails etc.
CLIENT: SAUDI ARAMCO
- LTA PROJECT - INSTALLING THE JACKET SFNY 1000 \ 1009
The project includes the installation of a jacket with 4 legs and 1 bay in SFNY field of Persian Gulf. The following activities were performed and supervised during the installation:
- Preparation activities for jacket installation and survey of the installation area
- Lifting, upending and positioning of the platform at the final position
- Jacket levelling
- Foundation piles installation: positioning, stabbing, hammering, add-on stabbing, welding and hammering until the target box. Installation of the piles according to the sequence
- Cutting portion of the piles for installation of transition pieces
- Installation of conductors piles according to the procedure
- Installing TDD, boatlanding and transition piece
- Completion work with installation of walkways, stairs, gratings, handrails etc.
CLIENT: SAUDI ARAMCO
- LTA PROJECT - INSTALLING THE JACKET ARBI 4
The project includes the installation of a jacket with 4 legs and 3 bays, single slope in ARBI field of Persian Gulf. The following activities were performed and supervised during the installation:
- Preparation activities for jacket installation and survey of the installation area
- Lifting and positioning of the platform at the final position
- Jacket levelling
- Foundation piles installation: positioning, stabbing, hammering, add-on stabbing, welding and hammering until the target box. Installation of the piles according to the sequence
- Cutting portion of the piles for installation of transition pieces
- Installation of a 32" conductor pile according to the procedure
- Installing TDD, boatlanding and transition piece
- Completion work with installation of walkways, stairs, gratings, handrails etc.
CLIENT: SAUDI ARAMCO
- LTA PROJECT - INSTALLING THE JACKET ARBI 5
The project includes the installation of a jacket with 4 legs and 3 bays, single slope in ARBI field of Persian Gulf. The following activities were performed and supervised during the installation:
- Preparation activities for jacket installation and survey of the installation area
- Lifting and positioning of the platform at the final position
- Jacket levelling
- Foundation piles installation: positioning, stabbing, hammering, add-on stabbing, welding and hammering until the target box. Installation of the piles according to the sequence
- Cutting portion of the piles for installation of transition pieces
- Installation of a 32" conductor pile according to the procedure
- Installing TDD, boatlanding and transition piece
- Completion work with installation of walkways, stairs, gratings, handrails etc.
CLIENT: SAUDI ARAMCO
- LTA PROJECT - INSTALLING THE JACKET HSBH 22
The project includes the installation of a jacket with 4 legs and 3 bays, single slope in HSBH field of Persian Gulf. The following activities were carried out and supervised during the installation:
- Preparation activities for jacket installation and survey of the installation area
- Lifting and positioning of the platform at the final position
- Jacket levelling
- Foundation piles installation: positioning, stabbing, hammering, add-on stabbing, welding and hammering until the target box. Installation of the piles according to the sequence
- Cutting portion of the piles for installation of transition pieces
- Installation of a 32" conductor pile according to the procedure
- Installing TDD, boatlanding and transition piece
- Completion work with installation of walkways, stairs, gratings, handrails etc.
CLIENT: SAUDI ARAMCO
- LTA PROJECT - INSTALLING THE JACKET HSBH 24
The project includes the installation of a jacket with 4 legs and 3 bays, single slope in HSBH field of Persian Gulf. The following activities were performed and supervised during the installation:
- Preparation activities for jacket installation and survey of the installation area
- Lifting and positioning of the platform at the final position
- Jacket levelling
- Foundation piles installation: positioning, stabbing, hammering, add-on stabbing, welding and hammering until the target box. Installation of the piles according to the sequence
- Cutting portion of the piles for installation of transition pieces
- Installation of a 32" conductor pile according to the procedure
- Installing TDD, boatlanding and transition piece
- Completion work with installation of walkways, stairs, gratings, handrails etc.
CLIENT: SAUDI ARAMCO
- LTA PROJECT - INSTALLING THE JACKET HSBH 19
The project includes the installation of a jacket with 4 legs and 3 bays, single slope in HSBH field of Persian Gulf. The following activities were performed and supervised during the installation:
- Preparation activities for jacket installation and survey of the installation area
- Lifting and positioning of the platform at the final position
- Jacket levelling
- Foundation piles installation: positioning, stabbing, hammering, add-on stabbing, welding and hammering until the target box. Installation of the piles according to the sequence
- Cutting portion of the piles for installation of transition pieces
- Installation of a 32" conductor pile according to the procedure
- Installing TDD, boatlanding and transition piece
- Completion work with installation of walkways, stairs, gratings, handrails etc.
CLIENT: SAUDI ARAMCO